M E M O   /   N O T E   D E   S E R V I C E

 

 


 

 

To / Destinataire

Mayor and Members of Council/ Maire et Membres du Conseil ToMayor and

File/N° de fichier:  ACS2008-CPS-HOU-0002-IPDFile Number

From / Expéditeur

FromRussell Mawby, Director, Housing/ Directeur Logement Directeur, Logement Directeur, Logement

 

Subject / Objet

SubjectFinal Allocations of Grants to Social Housing Providers for Capital Repairs/ Répartition finale des subventions aux fournisseurs de logements sociaux en vue de la réparation des biens immobiliers

Date: 8 January 2008/8 janvier 2008 Date3 3

 

 

On October 24, 2007, Council approved the allocation of $12 million in grants to social housing providers in support of emergency repairs. Council directed that $6 million of the total was to be allocated to Ottawa Community Housing Corporation (OCHC).  An update on the implementation process was provided to CPS committee on November 15th.  A final report was promised following the final allocation date of November 30th.

 

The transfer of $6 million to Ottawa Community Housing was completed in October.

 

In addition to OCHC, thirty-one other social housing providers applied for urgent capital funding. Many housing providers applied for multiple projects, and in total, one hundred and twenty three separate projects were reviewed. Requests exceeded available funding by $5.126 million.  All thirty-one housing providers had at least one project which qualified for priority funding. Eighty-nine projects were approved to receive funding and letters have been sent to the housing providers. The remaining thirty-four projects could not be funded due to a lack of funds.  Per standard accountability with third parties, funds will be paid based on invoices as projects meet defined milestones. Most of the work is getting started.  Some of the work has already been completed and the funds have been transferred to those agencies.  All projects must be completed and funds paid by December 31, 2008. 

 

The review of applications from the thirty-one housing providers (other than OCHC) has confirmed the need for funding for urgent repairs. Because the funding process was based on detailed estimates and assessments of repairs or replacement requests, both staff and housing providers have a much better understanding of issues and future liabilities in the social housing stock in Ottawa.

 

Many of the urgent repairs funded by this grant program are the result of more rapid failure of building systems than was expected in documented Building Condition Assessments.

 

In particular, many of the repair requests come from housing built in the 1990s that has experienced major and premature system failures. This housing was built at a time when most social housing was funded at a level that only allowed construction to minimum standards. This has resulted in very expensive capital expenditures on building systems that if adequately funded at the time would have lasted much longer.

 

One example is those buildings that were built with 15-year shingles rather than 25-year shingles. The material cost difference would have been minimal at the time, but the expense of having to replace the roofs 10 years before a normal replacement time adds considerably to the cost.  Staff have also noticed a failure of the stucco systems installed in many east end developments in the 1990s which allowed water to enter between the siding and the structure.  Not only does the siding have to be replaced, but as a result of the undetected failure over many years, there is usually mould and moisture damage to the structure of the buildings that must be remedied as well.  A number of elevators either need replacement or must be extensively refurbished to meet code requirements. The latter has to do with changes in legislation while the former speaks more to the quality of the original elevator purchased.

 

Although thirty-one housing providers (not including OCHC) applied for urgent capital funding, twenty-six did not. Staff are concerned that some of those providers who did not apply also have urgent capital needs but did not follow through with an application for funding. Staff are in the process of conducting site visits or mini operational reviews with all housing providers. These site visits will be completed in 2008, and it is anticipated that the information from these visits will provide more intelligence with regard to the state of capital needs.

 

Major areas where funding was focused:

 

Roof replacement/repair

$1.6 million

Siding Replacement/repair (including brick work)

$2.2 million

Elevator Replacement/repair

$1.5 million

Miscellaneous items (eg: balcony Repairs, Asbestos removal, Retaining wall replacement, Window replacement, Assessments etc)

$  .7 million

 

 

Total  

$6.0 million

 

Example of Projects that exceeded the funding included:

 

Elevator modernization/replacement/repair

Asbestos Management

Siding Replacement/repair

Foundation Repair

Window Repair/replacement

Balcony and Deck repairs

Roof replacement/repair

Parking garage repairs

Appliance replacement

Interior upgrades (kitchens and bathrooms)

General interior improvements (painting, carpeting

 

Total requests exceeding funds available by $5.126 million

 

Total requests and allocations are set out in the attached table.

 

Author Russell Mawby

 

Author’s Initials RM/ Prepared by InitialsRM

 

 

Attach. 

 

cc:     City Manager

          Deputy City Manager, Community and Protective Services

          Director, Housing

           


 

Housing Provider

Urgent Repairs/Needs Issue item

Total Cost of Job

Amount Approved (within $6,000,000 limit)

Asher Christian

BCA

8,448

8,448

Asher Christian Total

 

8,448

8,448

Barrhaven NP

Window & Roof Assessment & Report by Laviolette Engineering (2 invoices)

2,279

1,500

Barrhaven NP

Replacement of roof

105,088

83,816

Barrhaven NP

Replacement of windows

179,247

14,684

Barrhaven NP Total

 

286,614

100,000

Better Living Coop

Additional eng. studies incl. thermography & unit heating cost analysis

10,600

10,600

Better Living Coop

Roofs

109,975

109,975

Better Living Coop

Windows

204,050

0

Better Living Coop

Siding Replacement Final Block

204,050

0

Better Living Coop

Install add't insulation & air/vapour barrier

265,000

0

Better Living Coop

Eavestroughs

27,825

0

Better Living Coop Total

 

821,500

120,575

Cartier Square Coop

Repair Elevators

19,822

19,822

Cartier Square Coop Total

 

19,822

19,822

CCOC

Localized roof repairs

22,578

22,578

CCOC

Localized replace damaged brick, repoint & recaulk

60,327

60,327

CCOC

Replace damaged brick, repoint & recaulk (entire bldg)

261,963

261,963

CCOC

Elevator Replacement

291,500

145,750

CCOC

Elevator Replacement

291,500

145,750

CCOC

Elevator Replacement

291,500

145,750

CCOC

Elevator Replacement

291,500

145,750

CCOC

Elevator Replacement

291,500

145,750

CCOC

Concrete Repairs to Parapet

219,420

0

CCOC Total

 

2,021,788

1,073,618

Chinese Community

Repair balcony slab study

1,500

1,500

Chinese Community

Repair elevator #2

6,440

3,400

Chinese Community

Repair roof leakage

12,230

12,230

Chinese Community

Inspection of asbestos

3,150

3,150

Chinese Community

Repair brick distress problem

304,820

304,820

Chinese Community

Replacement of roofs

190,512

180,700

Chinese Community

Replacement of heating boiler

15,523

15,523

Chinese Community

Costs for modernization of elevators

385,560

0

Chinese Community

Replacement of windows & patio doors

254,016

0

Chinese Community

Replacement of overhead garage door & repair parking garage

14,112

0

Chinese Community

Interior finishes (painting, carpeting)

43,747

0

Chinese Community

Improvements of unit interiors (bathroom & kitchen upgrades, fridge replacements)

381,024

0

Chinese Community

Renovation of Unit #101

16,411

0

Chinese Community Total

 

1,629,045

521,323

Communityworks NP

Consultant Fees

1,500

1,500

Communityworks NP

BCA

6,784

6,784

Communityworks NP

Repairs to elevators

81,529

81,529

Communityworks NP

Repairs to elevators

23,669

23,669

Communityworks NP Total

 

113,482

113,482

Conservation Coop

EIFS exterior wall cladding (stucco wall)

360,000

360,000

Conservation Coop Total

 

360,000

360,000

Cote Est Coop

Balcony Surface

33,579

33,579

Cote Est Coop

Roof

92,000

92,000

Cote Est Coop

Retaining Wall

20,000

20,000

Cote Est Coop

Balcony Structural interface

43,000

43,000

Cote Est Coop

Windows

110,000

110,000

Cote Est Coop

Hot Water Tanks

83,300

0

Cote Est Coop

Fence

7,000

0

Cote Est Coop Total

 

388,879

298,579

Cumberland NP Housing

Consultant Fees

1,500

1,500

Cumberland NP Housing

Roofing Gate 2007

10,057

10,057

Cumberland NP Housing

Stucco replacements Gate 2007

26,986

26,986

Cumberland NP Housing

Roofing Gate 2008

124,845

124,845

Cumberland NP Housing

Stucco replacement Gate 2008

301,088

294,688

Cumberland NP Housing

New siding

57,350

55,350

Cumberland NP Housing Total

 

521,826

513,426

Dalhousie NP

Consultant Fees

1,500

1,500

Dalhousie NP

Roofing - 27 units (spread over 3 separate bldg sites)

35,878

35,878

Dalhousie NP  Total

 

37,378

37,378

Daybreak

BCA

6,500

6,500

Daybreak Total

 

6,500

6,500

Desloges Coop

Engineering study: Elevator repair

1,500

1,500

Desloges Coop

Elevator repair

265,500

253,500

Desloges Coop Total

 

267,000

255,000

Dobbin Coop

Roof replacement

180,497

180,500

Dobbin Coop Total

 

180,497

180,500

Emily Murphy NP

Roof Replacement

64,903

64,903

Emily Murphy NP

Siding Replacement Final Block

28,592

28,592

Emily Murphy NP Total

 

93,495

93,495

Gloucester NP

Install vapour barrier, remove & replace damaged rim board, floor joists, insulation & non functioning heaters

21,200

21,200

Gloucester NP

Consultant Fees

1,500

1,500

Gloucester NP

Roofing

21,200

21,200

Gloucester NP

Roofing

22,260

22,260

Gloucester NP

Siding

244,028

244,028

Gloucester NP

Siding

43,915

43,915

Gloucester NP Total

 

354,103

354,103

Kanata Baptist Place

Keller Engineering Assoc. Invoice for RLF Applic.

929

929

Kanata Baptist Place

Study of Concrete Balcony & Deck Repairs

4,000

4,000

Kanata Baptist Place

Fire Alarm Panel & Smoke Detector Replacement

30,000

30,000

Kanata Baptist Place

Brick veneer repairs (townhouses)

120,000

120,000

Kanata Baptist Place

Concrete Balcony & Deck Repairs

30,000

0

Kanata Baptist Place

Exterior Door Replacements (townhouses)

105,000

0

Kanata Baptist Place

Furnishing & Appliance Allowance

15,000

0

Kanata Baptist Place

Exterior Concrete Curb Repair Allowance

25,000

0

Kanata Baptist Place

Balcony & Townhouse Railing Painting

25,000

0

Kanata Baptist Place

Various Interior Finishes

105,000

0

Kanata Baptist Place

Asphalt Pavement

180,000

0

Kanata Baptist Place

Concrete Balcony Waterproofing

70,000

0

Kanata Baptist Place Total

 

709,929

154,929

King's Daughters & Sons

Consultant Report

1,500

1,500

King's Daughters & Sons

BCA

3,000

3,000

King's Daughters & Sons

Roof Replacement

116,000

0

King's Daughters & Sons

Elevator modernization program

174,000

0

King's Daughters & Sons

Asbestos management plan

3,480

0

King's Daughters & Sons

Window Replacement

150,800

0

King's Daughters & Sons

Brick Repairs

17,400

0

King's Daughters & Sons

Main Entrance Door

11,600

0

King's Daughters & Sons

Card Access System

5,000

0

King's Daughters & Sons Total

 

482,780

4,500

LIUNA

Repair to south wall of "10" units

129,320

129,320

LIUNA

Repair to south wall of the "02" & "03" units

140,980

140,980

LIUNA

Repair  to west wall of "03" units

156,880

156,880

LIUNA Total

 

427,180

427,180

Mario De Giovanni Coop

Repair roof - parapet walls, caulking & metal flashing

100,138

100,138

Mario De Giovanni Coop Total

 

100,138

100,138

Muslim NP

Repairs to elevators

20,034

20,034

Muslim NP

Garage Ramp repairs

85,000

85,000

Muslim NP

Replace windows

100,000

100,000

Muslim NP  Total

 

205,034

205,034

NCRV

Consultant Fees

1,500

1,500

NCRV

BCA

5,000

5,000

NCRV

Elevator Repairs

23,000

23,000

NCRV

Asbestos Management H&S

10,000

0

NCRV Total

 

39,500

29,500

Nepean Housing Corp.

Replacement of inverted flat roof

80,000

80,000

Nepean Housing Corp.

Replacement of 27 roofs

68,000

68,000

Nepean Housing Corp.

Replacement of 54 roofs

171,720

171,720

Nepean Housing Corp. Total

 

319,720

319,720

OCISO

Consultant Fees

1,193

1,193

OCISO

Replacement of traction sheave brake on 2 elevators

20,034

20,034

OCISO

Modernization of elevator motor & control systems

271,040

271,040

OCISO

Investigation & repair of masonry/foundation leaks into # 108

22,260

22,260

OCISO

Investigation & repair/replacement of penthouse roof & siding

12,561

0

OCISO Total

 

327,088

314,527

Rideau NP Housing Inc.

Consultant Fees

1,500

1,500

Rideau NP Housing Inc.

BCA

6,500

6,500

Rideau NP Housing Inc.

Refund some $ from balcony support posts, repair walkways, balcony decks & replace windows (34)

138,708

120,893

Rideau NP Housing Inc. Total

 

146,708

128,893

Serson Clarke NP

Elevator Repair

10,059

10,059

Serson Clarke NP

Make up Air exchanger

25,000

10,500

Serson Clarke NP

Parking Ramp

70,000

0

Serson Clarke NP Total

 

105,059

20,559

Shefford Heritage

Consultant fees

1,312

1,312

Shefford Heritage

Assessment of Attic insulation & update hazardous materials management plan

940

940

Shefford Heritage

Flat roof replacement & roof detailing repairs

157,800

157,800

Shefford Heritage

Plumbing Drain & ventilation stack replacement

536,726

56,575

Shefford Heritage  Total

 

696,778

216,627

Shikun Oz

BCA

7,920

7,920

Shikun Oz Total

 

7,920

7,920

St. Georges Coop

Removal of possible friable & non-friable asbestos material in 8 older homes

5,060

5,060

St. Georges Coop

Repair foundation walls

264,000

0

St. Georges Coop Total

 

269,060

5,060

St. Vlad's NP

Consultant Fees

1,500

1,500

St. Vlad's NP

BCA

8,989

8,316

St. Vlad's NP

Asbestos Management H&S

10,000

0

St. Vlad's NP

Atrium Window Replacement

63,600

0

St. Vlad's NP

Emergency Generator

95,400

0

St. Vlad's NP Total

 

179,489

9,816

West Carleton

BCA

6,500

6,500

West Carleton Total

 

6,500

6,500

Grand Total

 

$11,133,259

$6,007,152