Report to/Rapport au :

Corporate Services and Economic Development Committee

Comité des services organisationnels et du développement économique

 

and Council/et au Conseil

 

5 August 2003/le 5 aout 2003

 

Submitted by/Soumis par :  Steve Kanellakos, A/City Manager/
Directeur des services municipaux intérimaire

City Manager’s Office, Bureau du directeur des services municipaux

And

Jocelyne St. Jean, General Manager, People Services Department /
Directrice générale, Services au citoyens

 

Contacts/Personnes-ressource :  Réjean Chartrand, Director, Strategic Delivery Unit/Directeur, Unité d’exécution stratégique

580-2424, ext. 21696, Rejean.Chartrand@ottawa.ca

and Colleen Hendrick, Director, Innovation, Development and Partnerships/

Directrice de l’Innovation, development et partenariat,

724-4122, Ext./poste 24366, Colleen.Hendrick@ottawa.ca

 

 

 

 

Ref N°:   ACS2003-CMR-OCM-0008

 

 

SUBJECT: PUBLIC-PRIVATE PARTNERSHIP (P3) PROJECT –
DOMED / INDOOR PLAYING FACILITIES

 

OBJET : PROJET DE PARTENARIAT PUBLIC-PRIVÉ (3 P) –

STRUCTURE DE JEUX INTÉRIEURE EN FORME DE DÔME

 

 

REPORT RECOMMENDATIONS

 

That the Corporate Services and Economic Development Committee recommend Council:

 

1. Authorize staff to enter into negotiations with Thunderbird Management Services Inc. (TMSI) for the construction and operation of a year round, air supported, domed playing facility at Hornet’s Nest on Bearbrook Road; and

 

2. Direct staff to report to Council on the outcome of the negotiations in September 2003.

 

 

RECOMMANDATIONS DU RAPPORT

 

Que le Comité des services organisationnels et du développement économique recommande au Conseil municipal :

 

1. d’autoriser le personnel à entreprendre les négociations avec la société Thunderbird Management Services Inc. (TMSI) en ce qui concerne la construction et l’exploitation durant toute l’année d’une structure de jeux gonflable en forme de dôme au Hornet’s Nest situé sur le chemin Bearbrook;

 

2. de demander au personnel de fournir au Conseil municipal un compte rendu portant sur les résultats des négociations en septembre 2003.

 

 

BACKGROUND

 

In October 2002, City Council approved that a number of projects be implemented on a priority basis under public-private partnerships, including the provision of domed / indoor playing facilities.

 

A Request for Proposal (RFP) for Domes / Indoor Playing Facilities was issued 4 April 2003 on MERX by the Supply Management Division.  The RFP closed on 8 May 2003, and two qualified submissions were received from:

 

 

After evaluating the two proposals, it was deemed that both proposals were non-responsive to the City’s requirements; and therefore, the RFP process came to an end.  Discussions were held internally with the decision that the City would consider a year round structure subject to the project being implemented at no net cost to the City. The two respondents were invited to submit proposals based on these parameters, and proposals were received from both firms at the end of June.

 

This report recommends that staff enter into negotiations with TMSI for the construction and operation of a domed / indoor playing facility at Hornet’s Nest on Bearbrook Road.  As per Council direction, a public meeting will be held in the community during this stage.

 

 

DISCUSSION

 

The RFP invited respondents to submit proposals for the construction and operation of an air supported seasonal domed playing field on two City locations – Hornet’s Nest on Bearbrook Road and Minto field at the Nepean Sportsplex. 

 

At Hornet’s Nest, there are currently 12 soccer pitches of natural turf and a clubhouse constructed in 2000 that is on a septic and well system.  The pitch closest to the parking lot is the proposed site for development.  The natural turf would be replaced with an artificial turf system as part of the dome installation.  Improvements to the parking area and an upgrade of the power source would also be required. 

 

The fields are currently operated under the terms of an agreement between the City of Ottawa and the Gloucester Soccer Association (GSA).  The GSA has exclusive use of the clubhouse and food concession.  They also have exclusive rights to the playing fields for the soccer season approximately June 1 to September 30, making the field available to the private sector partner from approximately the beginning of October to the end of May.

 

Minto Field is located east of the Nepean Sportsplex main parking area.  The field is on property covered by a long-term lease between the City and the National Capital Commission.  The playing surface is an artificial turf that was first used in Spring 2001.  In order to accommodate a dome, services would need to be extended from the front of the property to the field perimeter.  The field is currently fully booked with long-term users from approximately the second week of April to the second week of November.  The site would therefore be available to the private sector partner from approximately mid November to the first week in April.

 

 

The Request for Proposal Stage

 

Proposals were received from TMSI and The Farley / 1v1 Partners.  The evaluation team, comprised of representatives from the People Services Department, RPAM, the Strategic Delivery Unit, and an external representative, evaluated each proposal considering the stated objectives of the City and using the established detailed evaluation criteria. These criteria were known to all proponents since they formed part of the RFP. 

 

Neither proposal expressed an interest in developing Minto Field at this time.  The shorter operating season was cited as a deterrent.  Both proposals detailed developing Hornet’s Nest and required the City to pay for the site preparation and installation of artificial turf.  Additional conditions included a year round structure or the City to pre-purchase field time and assume all risk.  For all these reasons, the proposals were deemed non-responsive and the RFP process closed.

 

The submissions, as well as feedback from potential proponents received during the process, indicated there either needed to be a change to the overall parameters of the project or the City would have to be more involved in order for a viable business case to be established.  It became clear that a year round structure provided the best scenario, minimizing the City’s risk exposure and providing the necessary revenue required by the private sector.

 

A year round structure would, however, place pressure on the well capacity and septic system.  The current well capacity would not meet the water requirements under the fire code. The year round usage with a larger concession would also put pressure on both water and septic systems.  Permanent services would be required, and could be provided by extending the water main along Bearbrook Road to the Hornet’s Nest site and by installing a sewage lift station with a 100mm. diameter force main to connect to existing services on Bearbrook Road.

 

Discussions were held internally with the decision that the City would consider a year round structure subject to the project being implemented at no net cost to the City.  Both proponents submitted revised proposals under these conditions.  One proponent proposed developing the Hornet’s Nest now and developing Minto Field at a later date.  The conditions for development of Minto Field were unacceptable to the City and therefore, Minto Field was removed from consideration, leaving Hornet’s Nest as the sole site.

 

Both proposals were evaluated and TMSI was deemed to be the preferred respondent, providing the City with the best value.  Staff recommends that the City enter into negotiations with TMSI to develop an agreement for the construction, financing, and operation of a permanent facility at Hornet’s Nest at no net additional cost to the City.

 

 

ENVIRONMENTAL IMPLICATIONS

 

An external consultant to the City carried out a study at the Hornet’s Nest site in April 2003.  It was noted that with attention to site preparation, drainage design and proper construction practices, the addition of a structure would have minimal impact on water drainage and the environment.

 

 

RURAL IMPLICATIONS

 

The facility will be available to users from across the City, including rural residents who will have access to the new indoor field.

 

 

CONSULTATION

 

The Gloucester Soccer Association was consulted during all phases of this process and confirm their support for the City to proceed.  They have committed to negotiate an agreement with TMSI on the use of the clubhouse and the soccer field. 

 

A public meeting will be held during the negotiations process with the private sector partner prior to the execution of a P3 partnership agreement.

 

 

FINANCIAL IMPLICATIONS

 

Negotiations with TMSI will be undertaken to form an agreement that will result in no net additional costs to the City.

 

 

ATTACHMENTS

 

None.

 

 

DISPOSITION

 

The Strategic Delivery Unit and People Services Department will implement the recommendations as directed by Council.