1. King
Edward Avenue Renewal
Renouvellement de l’avenue King
Committee Recommendations As Amended
Having held a public hearing, that Council approve:
1.
The renewal of King Edward
Avenue as per the Recommended Design and Streetscape Demonstration Plan
described herein.
2.
The filing of the Environmental
Study Report (ESR) in accordance with the Environmental Assessment Act for the
renewal of King Edward Avenue.
3. That
the 4-lane option for King Edward be reviewed for the feasibility of
implementation when each of the:
a. Transportation
Master Plan
b. The
Rapid Transit Expansion Study;
c. The
East End Interprovincial Bridge Study; and,
d. The
implementation of the CN-CP proposal to twin freight lines between Ottawa and
Toronto to carry inter-city truck traffic;
are brought forward to
Transportation and Transit Committee.
Recommandations Modifiées du comité
Une audience publique ayant eu lieu,
que le Conseil approuve:
1.
Le
renouvellement de l’avenue King Edward conformément à la conception recommandée
et au plan de paysage de rue que décrit le présent rapport.
2.
La
présentation du rapport de l’étude environnementale menée conformément à la Loi
sur l’évaluation environnementale, en vue du renouvellement de
l’avenue King Edward.
3.
l’examen de l’option à quatre voies pour l’avenue King Edward en ce qui
concerne la faisabilité et la mise en place, quand :
a. le
Plan directeur des transports;
b. l’Étude
sur l’expansion des services de transport en commun rapide;
c. l’Étude
sur le pont inter-provincial de la partie est;
d. la mise en place de la proposition
de CN et de CP visant à jumeler les lignes de marchandises entre Ottawa et
Toronto afin de transporter les marchandises acheminées par camion entre les
deux villes;
auront été soumis au Comité des
transports et des services de transport en commun.
Documentation
1.
General
Manager, Transportation, Utilities and Public Works report dated 14 June 2002
is immediately attached (ACS2002-TUP-INF-0016).
2.
The
following submissions were received and are held on file:
a.
Chair,
City Centre Coalition letter dated 17 July 2002
b.
George
T. Wilson letter undated
c.
Mr.
& Mrs. Dey e-mail comments dated 10 July 2002
d. Chair, King Edward Avenue Task Force letter dated July 17, 2002
3.
Annexes A to F previously distributed to all members of Council.
4.
A
draft Extract of Minutes, 17 July 2002 will be distributed prior to Council and
will include the voting record.
Report to/Rapport au :
Transportation
and Transit Committee /
Comité des transports et des services de transport en commun
and Council/et au Conseil
14 June 2002/le 14 juin 2002
Submitted by/Soumis par: R.T.
Leclair, General Manager/Directrice générale
Transportation, Utilities and Public Works/Transport, services et Travaux
publics
580-2424,
ext. 21268, Richard.Hewitt@.ottawa.ca
|
|
Ref N°: ACS2002-TUP-INF-0016 |
SUBJECT: |
KINg edward avenue renewal |
OBJET: |
Renouvellement de l'avenue King Edward |
REPORT RECOMMENDATIONS
That the Transportation and Transit Committee recommend Council
approve:
3.
The renewal of King Edward
Avenue as per the Recommended Design and Streetscape Demonstration Plan
described herein.
4.
The filing of the Environmental
Study Report (ESR) in accordance with the Environmental Assessment Act for the
renewal of King Edward Avenue.
RECOMMANDATIONS DU
RAPPORT
Que
le Comité des transports et des services de transport en commun recommande au
Conseil d’approuver :
1. Le
renouvellement de l’avenue King Edward conformément à la conception recommandée
et au plan de paysage de rue que décrit le présent rapport.
2. La présentation du rapport de l’étude
environnementale menée conformément à la Loi
sur l’évaluation environnementale, en vue du renouvellement de l’avenue King Edward.
The City of Ottawa initiated the Planning and Environmental Assessment Study for the renewal of King Edward Avenue in early 2000. The study area includes the King Edward Avenue corridor from Laurier Avenue north to Sussex Drive, the connections at the south end of the Macdonald-Cartier Bridge, and the King Edward Avenue intersection with Sussex Drive. The study corridor is shown on Annexes ‘A’ and ‘B’.
King Edward Avenue is one of the principal roads within the eastern core area of Ottawa. It serves as a direct arterial road connection to the Macdonald-Cartier Bridge crossing of the Ottawa River to the City of Gatineau and beyond. It is the most direct freeway-to-freeway connection between provinces in the National Capital Region and is the primary inter-provincial truck route. It also serves as a collector road distributing traffic to streets within Lowertown, the Byward Market, Sandy Hill and the University of Ottawa, forming an integral portion of the core area neighbourhood street network.
King Edward Avenue was identified as a project in the former Region of Ottawa-Carleton's Urban Rehabilitation Program due to,
· The failed condition of the street's roadbed and pavement structure,
· The requirement for sewer separation in some sections,
· A need to replace the watermain along the length of the corridor.
As well, a 1999 Ontario Municipal Board (OMB) decision designated King Edward Avenue as a “First Priority” infrastructure project in the former Regional Official Plan. The project is now a priority of the new City of Ottawa.
The study process also took into consideration the 1993 King Edward Avenue Community Improvement Plan and the 1996 King Edward Avenue Improvement Project Development Plan, which were approved by the former Region of Ottawa-Carleton and the former City of Ottawa. These approved plans were intended to improve the street's social environment, visual character, and to encourage property investment and renewal along the corridor.
This study reinforced previous conclusions that there is a definite need to renew King Edward Avenue. For purposes of this study, "renewal" has been defined as the replacement/upgrading of failed infrastructure and the creation of an environment within the corridor that will improve the safety of all travel modes and the environment and quality of life of residents and users of the corridor.
The study process has resulted in a “Preferred Design” for the renewal of King Edward Avenue and a “Streetscape Demonstration Plan” for the corridor. Also developed, were options that show how the preferred design is compatible with possible roadway reduction to four lanes, should this be a recommended course of action at some future time.
In arriving at these recommendations, the study considered:
· the traffic carrying function of the corridor (including all traffic modes and vehicle types) along and across King Edward Avenue;
· the safety and security of all users of the corridor including pedestrians, cyclists and vehicle occupants;
· the opportunities to reduce the adverse environmental affects of the current vehicular use of the corridor on adjacent residents, businesses, and users;
· the potential adverse environmental effects caused by the construction of the project; and
· the development of a streetscape demonstration plan and a strong urban design statement that reflects King Edward Avenue’s function as a civic boulevard and gateway into the Central Area.
The King Edward Avenue corridor currently operates at or over its vehicular capacity. A premise of this study was the current volume of traffic had to be accommodated in the preferred renewal solution. Lane reduction options that would reduce the road’s capacity and further decrease the existing poor levels of service were not recommended. All other interprovincial bridge crossings are currently operating at or close to their capacity. There are no short-term options to accommodate the magnitude of displaced traffic that a lane reduction scenario on King Edward Avenue would trigger.
The project has proceeded under the direction of the City of Ottawa with support from the National Capital Commission (NCC) and Public Works and Government Services Canada (PWGSC). The project has benefited from the direct involvement and guidance of a Technical Advisory Committee (TAC) and a Public Advisory Committee (PAC). Public consultation with corridor users, interest groups and the general public also formed an integral part of the entire study framework.
Given the potential effect of renewal of the corridor on federally owned lands, the study was planned in accordance with the requirements of the Canadian Environmental Assessment Act, the National Capital Commission's Environmental Assessment Policy, and the Ontario Municipal Engineers Association Municipal Class Environmental Assessment.
Once the preferred design solution was identified, it was determined that the renewal project was a Schedule ‘C’ Municipal Class Environmental Assessment (EA) and that Federal EA requirements had not been triggered.
The four sections, shown on Annex ‘C’ as
South, Central South, Central North and North, best describe the King Edward
Avenue study corridor. Each section has
unique characteristics and issues.
South Section
The South Section extends from Laurier Avenue north to Rideau
Street. This section has an existing
right-of-way (ROW) of approximately 20 m, four traffic lanes and no
median. On-street parking is permitted
along some blocks in off-peak periods.
The designated ROW in the Official Plan is 23 m. This section is located
within the Sandy Hill community, just north of the University of Ottawa. Low and medium density residential and
institutional uses flank the roadway with predominantly small building
setbacks. Issues in this section
include:
·
aged
underground infrastructure needs replacing;
·
at-grade
infrastructure including the road surface, curbs and sidewalks needs renewal;
·
narrow
sidewalks;
·
traffic
congestion during peak hours.
Pedestrian, bicycle, vehicle traffic and truck data along this section and at its two key intersections are summarized in Table 1. There are no transit buses on this section of King Edward Avenue.
Table 1: South
Section Existing Traffic Conditions
|
Location |
||
King Edward South of
Rideau |
Laurier / King Edward |
Rideau / King Edward |
|
Pedestrian volume |
|||
- peak commuter hour |
N.A |
780 |
960 |
- daily |
N.A. |
2,900 |
5,500 |
Bicycle volume |
|
|
|
- peak hour |
N.A. |
90 |
60 |
- daily |
N.A. |
585 |
410 |
Heavy Truck traffic (two-way total) |
|||
- peak |
40 (2%) |
N.A. |
N.A. |
- daily |
225 (1%) |
N.A. |
N.A. |
Vehicle traffic (two-way total) |
|||
- peak hour |
1,650 |
N.A. |
N.A. |
- daily |
17,000 |
N.A. |
N.A. |
Intersection Level of Service |
|||
- am peak hour |
N.A. |
F (failure) |
E (capacity) |
- pm peak hour |
N.A. |
F (failure) |
F (failure) |
Central
South Section
The Central
South Section extends from Rideau Street north to Murray Street. This section accommodates a six-lane roadway
within an existing and designated ROW of 40 m.
There are auxiliary turning lanes at some intersections. Residential, commercial, and institutional,
vacant properties and properties with redevelopment potential flank the
corridor. Curb-lane parking is
permitted in the off-peak periods.
Issues in this section include the same as those listed for the South
Section plus the following:
·
a
streetscape dominated by vehicles, asphalt, overhead power lines, traffic
signals, and traffic information signs;
·
higher speed
traffic, including a high percentage of truck traffic;
·
the lengthy
queue of southbound STO buses in the afternoon peak period that use the curb
lane as a time point to start their route;
·
a lack of
roadside or median vegetation (trees);
· a poor pedestrian environment in terms of comfort, mobility and safety.
Pedestrian, bicycle, transit, vehicle
traffic and truck data along this section and at its two key intersections are
summarized in Table 2.
Table 2: Central South
Section Existing Traffic Conditions
|
Location |
||
King Edward South of
Murray |
York / King Edward |
Murray / King Edward |
|
Pedestrian volume |
|||
- peak commuter hour |
N.A. |
200 |
110 |
- daily |
N.A. |
1,510 |
910 |
Bicycle volume |
|
|
|
- peak commuter hour |
N.A. |
30 |
65 |
- daily |
N.A. |
180 |
290 |
Heavy Truck traffic (two-way total) |
|||
- peak |
200 (7%) |
N.A. |
N.A. |
- daily |
2,600 (8.5%) |
N.A. |
N.A. |
Vehicle traffic (two-way total) |
|||
- peak hour |
2,800 |
N.A. |
N.A |
- daily |
30,600 |
N.A. |
N.A. |
Intersection Level of Service |
|||
- am peak hour |
N.A. |
C |
F (failure) |
- pm peak hour |
N.A. |
A |
F (failure) |
There are no OC Transpo buses on this section. There are a number of Société de Transport de L’Outaouais (STO) bus routes including a major afternoon peak hour time point on the southbound direction adjacent to the west curb. STO services comprise Regular Routes 30, 31, 33, 35, 48 and 44 and Express Routes 11, 17 and 83. In the order of 10 to 15 buses can be queued at the time point in the afternoon peak period.
Central North Section
The Central North Section extends from Murray Street north to Boteler Street. Its existing and designated ROW is 40 m., except from Bolton to Boteler where the existing ROW is approximately 46 m. A six-lane road plus auxiliary turn lanes exist and curbside parking is permitted in the off-peak periods. The main distinguishing characteristic of this area is it has a higher proportion of residential land uses, higher traffic volumes and traffic speeds than the Central South Section. There are few large vacant sites and fewer redevelopment opportunities in this area. The issues are similar to those for the Central South Section, although they are experienced more directly by residents due to the greater number of dwellings and their proximity to the roadway, higher traffic volume and higher speed.
Pedestrian, bicycle, transit, vehicles traffic and truck data along this section and at its two key intersections are summarized in Table 3.
Table 3:
Central North Section Existing Traffic Conditions
|
Location |
||
King Edward North of St. Patrick |
St. Patrick / King
Edward |
St. Andrew / King
Edward |
|
Pedestrian volume |
|||
- peak commuter hour |
N.A. |
85 |
65 |
- daily |
N.A. |
460 |
340 |
Bicycle volume |
|
|
|
- peak hour |
N.A. |
40 |
70 |
- daily |
N.A. |
180 |
170 |
Heavy Truck traffic (two-way total) |
|||
- peak |
200 (4%) |
N.A. |
N.A. |
- daily |
2,600 (5%) |
N.A. |
N.A. |
Vehicle traffic (two-way total) |
|||
- peak hour |
4,600 |
N.A. |
N.A. |
- daily |
50,000 |
N.A. |
N.A. |
Intersection Level of Service |
|||
- am peak hour |
N.A. |
E (capacity) |
C |
- pm peak hour |
N.A. |
F (failure) |
C |
There are no OC Transpo bus routes on this section. STO routes include Regular Route 48 and Express Routes 11 and 17.
North
Section
The North
Section has a much different character and land use pattern. There are existing on/off ramps to the
Macdonald-Cartier Bridge and connections to Sussex Drive and Union Street. The section has a sense of open space,
benefiting from adjacent parkland and scenic views to the Rideau River (along
the east side) and to the Ottawa River (along the north and west sides) and
beyond. Federal government buildings
anchor a secondary employment node along Sussex Drive in this section. An open space system with recreation paths
exists along the Rideau River. Issues
in this North Section include:
·
the
proximity of the southbound ramp to adjacent residences on Boteler Street;
·
the ramp
connections and grade separations to and from the Macdonald-Cartier Bridge that
promote higher speed vehicle movements along King Edward Avenue through the
Central North Section;
·
pedestrian
routes between the Central North Section and Sussex Drive are limited,
especially along the west side of the King Edward Avenue corridor;
·
inefficient
use of land due to the myriad of bridge ramps, overpasses, and connecting
roads;
·
the lack of
a “gateway” into the City of Ottawa for visitors travelling across the
Macdonald-Cartier Bridge into Ottawa.
Pedestrian, bicycle, transit, vehicles traffic and truck data along this section are summarized in Table 4.
Table 4: North
Section Existing Traffic Conditions
|
Location |
|
King Edward North of St. Andrew |
King Edward at
Macdonald-Cartier Bridge |
|
Pedestrian volume |
||
- peak hour |
N.A. |
20 |
- daily |
N.A. |
120 |
Bicycle volume |
||
- peak hour |
N.A. |
60 |
- daily |
N.A. |
380 |
Heavy Truck traffic (two-way total) |
||
- peak |
200 (4%) |
200 (3%) |
- daily |
2,600 (5%) |
2,600 (4%) |
Vehicle traffic (two-way total) |
||
- peak hour |
4,600 |
6,400 |
- daily |
50,000 |
67,250 |
There are no OC Transpo routes on this section. STO routes include Regular Route 48 and Express Routes 11 and 17.
Early in the process, “renewal” was confirmed as the preferred solution compared to doing nothing, or incrementally upgrading sections of failed infrastructure.
The next step considered a wide range of alternatives to redistribute traffic away from King Edward Avenue and possibly remove traffic lanes from King Edward Avenue. To facilitate renewal of the street at-grade, these alternatives included a number of tunnel options, an open cut option and a one-way pair option.
These are listed as follows:
· a tunnel under King Edward Avenue from the Macdonald-Cartier Bridge south to Mann Avenue;
· a tunnel under King Edward Avenue and Waller Street from the Macdonald-Cartier Bridge south to approximately Laurier Avenue;
· a tunnel under Dalhousie Street from the Macdonald-Cartier Bridge to approximately Waller Street;
· a tunnel from just north of St. Patrick Street to Nicholas Street just north of Laurier Avenue;
· a tunnel beneath the Rideau River from King Edward Avenue to the Vanier Parkway;
· a tunnel along the west side of the Rideau River from King Edward Avenue to intersect St. Patrick Street at approximately Beausoleil Street;
· an open cut, four-lane road along King Edward Avenue from Boteler Street south to Mann Avenue;
· conversion of King Edward Avenue and Dalhousie Street to a one-way pair;
· an at-grade roadway through the park adjacent to the west side of the Rideau River to connect King Edward Avenue to St. Patrick Street at approximately Beausoleil Street.
These alternatives were evaluated against numerous criteria under the headings, Natural Environment, Economic, Social Environment and Transportation. Based on a combination of community disruption, traffic operational issues at the tunnel portals, visual impacts of tunnel portals and construction costs (up to $250M for tunnels), none of the foregoing alternatives was recommended.
Other renewal alternatives included removing or adding traffic lanes to King Edward Avenue. The existing four-lane section from Laurier Avenue to Rideau Street was analyzed as both a two-lane and a six-lane road. The existing six-lane section from Rideau Street north to Bolten Street was analyzed as both a four-lane and an eight-lane road.
As background/input into the evaluation of these various traffic lane alternatives for King Edward Avenue, it is important to be aware of the following transportation related framework that guided the Planning and Environmental Assessment Study:
· a new interprovincial bridge will not be in place for a number of years. The King Edward Avenue corridor is scheduled for renewal over the next few years. On this basis, the renewal alternatives were evaluated, in part, on their ability to accommodate current traffic volumes at the current, or acceptable, levels of service;
· this study does not address truck bans or alternative corridors for interprovincial truck travel. Until such time as an alternate interprovincial truck route is agreed to and in place, the renewal alternatives will be evaluated, in part, based on their ability to accommodate truck traffic in the short-term;
· this study does not examine future Ottawa River bridge crossings and locations and whether a new bridge would redistribute traffic away from King Edward Avenue. This study does identify the volume of traffic that would have to be removed from King Edward Avenue in order for it to operate acceptably as a four-lane road instead of the current six-lane road (Rideau to Boteler).
The key factors against providing more lanes were insufficient existing right-of-way, potential displacement of existing trees and buildings (some heritage), adverse pedestrian circulation impacts and minimal roadway capacity/operational improvements.
The benefits of providing fewer lanes would be an improved social environment due to shorter pedestrian crossing distances, more space for streetscaping and landscaping and increased separation of the road from the adjacent land uses. These potential benefits, however, were offset by the significant adverse impacts on traffic flow within the existing congested corridor in peak periods. As there are currently no viable alternatives for the King Edward Avenue traffic, the results would be a further increase in congestion, an extension of the peak traffic periods, increased travel time, adverse impacts on transit service and a further reduction in air quality.
With this framework, and using the aforementioned evaluation criteria, the recommendation of this evaluation phase was lane reductions or lane additions were not appropriate and the preferred renewal solution was to retain the current number of lanes on King Edward Avenue. These lanes could be reconfigured but the number had to be retained.
Having determined the preferred renewal alternative for King Edward Avenue south of Bolton Street (South and Central Sections) was to retain the current number of lanes, in some configuration, the evaluation then focussed on the North Section.
Eight alternatives were identified/developed for the North Section and the same evaluation criteria/process was applied. The alternatives included different versions of roadway relocation options, 'T' intersection options and a roundabout option.
The preferred renewal alternative for the North Section maintained a free flow King Edward Avenue but included significant roadway relocation. It is shown on Annex ‘D’ and included:
· location of the southbound ramp away from the Boteler Street residences;
· relocation of the northbound ramp to a lower elevation and adjacent to the new southbound ramp;
· realignment of the northbound connection to Sussex Drive away from the Rideau River and reduction from two-lanes to one;
· realignment of the southbound connection from Sussex Drive to merge with southbound King Edward Avenue on the right and not on the left, as it currently does.
This alternative was recommended through the evaluation process as it maintains the critical current traffic carrying capacity in the North Section while resulting in significant improvements to the social environment and to the pedestrian and bicycling environments. Annex ‘E’ depicts the combined preferred renewal alternatives for each of the four Sections of King Edward Avenue.
The next step was to develop alternative designs for the preferred renewal alternative. To assist on this step, Planning and Design Principles were developed and documented. These were reviewed by TAC and PAC. Technical specifications were also used, some of which were based on the former Regional Road Design Guidelines, as were Official Plan policies and objectives related to walking, cycling, transit, goods movement, community values, views and vistas, streetscaping and gateway development. The design will meet or exceed the current Sidewalk Technical Design Guidelines.
Technical design criteria used to develop the alternative designs for the preferred renewal alternatives included:
|
|
width |
· through lane |
………… |
3.25 m |
· lane adjacent to curb |
………… |
3.50 m |
· bridge connecting lanes |
………… |
3.75 m |
curb-side shared-use lane |
|
|
- north of Rideau |
………… |
4.5 m |
- south of Rideau |
………… |
4.0 m |
- south of Rideau up the hill to Stewart |
…………… |
4.2 m |
· left-turn lanes not adjacent to a curb |
………… |
3.25 m |
· one-way single lanes |
………… |
5.0 m |
· sidewalks (minimum) |
………… |
2.0 m |
South Section
For the South Section (Laurier to Rideau), given the narrow right-of-way (approximately 20 m) and adverse impacts of widening this right-of-way, there was only one design alternative. It is described as follows and is shown on Annex ‘E’.
· one 3.25 m through-lane in each direction;
· 4.0 m curb-side shared vehicle/cycling lane in the northbound direction, and in the southbound direction between Stewart Street and Laurier Avenue (in the relatively flat portion) that could also be used as off-peak parking lanes in some locations;
· 4.25 m curb-side shared vehicle/cycling lane in the southbound direction between Rideau Street and Stewart Street (slightly wider for the uphill portion) that could also be used as off-peak parking lanes in some locations;
· an approximate 2.5 m to 2.75 m road edge along each side, which would include a minimum sidewalk width of 2.0 m wherever possible.
In some locations the ROW narrows to 19 m in the South Section. In addition, there are some building encroachments into the ROW that narrow it further. In these locations, the sidewalks may be as narrow as 1.5 m. All efforts were made to achieve the desired 2.0 m sidewalk, where possible.
Central South and Central North
Sections
For the purposes of presenting and evaluating the alternative designs, the Central South and Central North Sections were considered simultaneously. This was primarily because these sections each have an existing and designated right-of-way of approximately 40 m and the preferred renewal alternative for each has been confirmed as a six-lane roadway.
Three Alternative Designs for the Central South and Central North Sections were identified as being reasonable alternatives worthy of detailed evaluation.
The major variable of each design is the
median width. The median width is
either wide (8.0 m) or narrow (1.5 m), with the application varying between the
Central North and Central South Sections.
The following is a description of each of
the three Alternative Designs:
Alternative Design 1: Wide Median
The defining characteristics of Alternative Design 1 are:
· 8.0 m wide median wherever possible (median narrows to less than 8.0 m where turning lanes are required);
· 4.75 m (approximate) road edge (boulevard), which includes a 2.0 m sidewalk.
Due to the requirement for turning lanes in various locations along the corridor, the median remains 8.0 m wide only in the block between Cathcart Street and St. Andrew Street, and in the block between Murray Street and York Street. In the blocks between St. Andrew Street and Murray Street, the median is reduced to 1.5 m where double left-turn lanes have been taken from the median.
In this Alternative Design, the vehicle lanes do not deflect and therefore remain straight (parallel to the road edge) between Rideau Street and Cathcart Street. This is one of the defining characteristics of the alternative.
Alternative Design 2: Narrow Median
The defining characteristics of Alternative Design 2 are:
· 1.5 m wide median (median widens to 8.0 m between Murray Street and York Street to oppose the southbound double left-turn at St. Patrick Street);
· 8.0 m (approximate) road edge (boulevard), which includes a 2.0 m sidewalk.
The median width remains constant at 1.5 m except for the block between Murray Street and York Street, where it is expanded to between 4.0 m and 7.5 m to oppose the southbound double left-turn lanes at St. Patrick Street. In this option, the through lanes deflect around turning lanes, but to acceptable design standards.
Alternative Design 3: Combination Wide/Narrow Median
The defining characteristics of Alternative Design 3 are:
· between Rideau Street and Murray Street, the design uses the wide median option (as in Alternative Design 1);
· between Cathcart Street and Murray Street, the design uses the narrow median option (as in Alternative Design 2).
Other Design Alternatives
Considered But Screened Out
Two other
options were considered but screened out before undergoing a detailed
evaluation. The first alternative was
basically the opposite of Alternative Design 3, based on a narrow median
between Rideau Street and Murray Street option (as in Alternative Design 2),
and a wide median between Cathcart Street and Murray Street option (as in
Alternative Design 1). A wide median in
the Central North Section would result in a narrow road edge and minimal
separation of vehicle lanes and residences that basically would reflect
existing conditions. This alternative
shares none of the benefits of Alternatives 2 and 3 in the Central North
Section and also has none of the benefits of Alternative 1 in the Central South
Section (wider median to oppose the southbound double-left turns onto St.
Patrick Street). For these reasons,
this other alternative was not deemed to be a reasonable alternative for
further detailed evaluation.
The second alternative considered but
screened out an option with no median.
Having no median along the Central South and Central North Sections was
deemed to be an unreasonable option and not worthy of detailed evaluation for
two reasons. Given the width of King
Edward Avenue, medians are required to accommodate some of the traffic signal
plant. Medians are also required to
restrict turning movements, particularly left-turn movements onto side streets,
and left-turn movements from side streets across the roadway. The failure to restrict these movements
would severely disrupt the capacity and operation of the road during peak
hours, thereby increasing vehicle congestion that would in turn lead to
diminished neighbourhood air quality.
These movements would also reduce road safety for pedestrians and
motorists. Also, medians are required
to oppose turning lanes at St. Patrick and York Street, even if painted, so
under no scenario could the roadway be entirely free of medians of some type.
Central North and Central South Sections Preliminary Preferred Design
The Central Section design alternatives were evaluated against the following four primary criteria groupings: Natural Environment, Economic Environment, Social Environment and Transportation Conditions. Within these groupings, there were a total of 31 criteria.
Alternative Design 2: Narrow Median was by far the preferred alternative following evaluation. It was the best for 16 of the criteria and equally preferred for 12.
The preliminary preferred
design (narrow median) for the Central Sections is shown on Annex ‘E’. The following are the key factors that
contribute to the preferred narrow median option:
·
it
relocates traffic lanes as far away from adjacent residences as possible,
thereby maximizing the opportunity to improve air quality, noise, and vibration
conditions for land uses along the corridor;
·
it provides a
greater opportunity for gateway treatments;
·
it
consolidates useable land in the road edge for use as landscaping, sidewalks,
street furniture, and snow storage, as well as for the burying of overhead
wires;
·
it
provides the best conditions for greenspace and tree survival;
·
it
provides the most pedestrian and transit friendly environment in the road edge;
·
by
reducing crosswalk distances, it best integrates neighbourhoods on the east and
west sides of the street;
·
it
will have the greatest potential to calm traffic by presenting the sense of a
narrower corridor thereby reducing vehicle speeds;
·
by
improving environmental conditions along the road edge, it is more likely to
provide the best stimulus for property investment and renewal along the
corridor;
·
it
provides the most flexibility for construction phasing and staging;
·
it
maximizes opportunities to keep the transportation system as operational as
possible during construction;
·
it
provides more choices for possible future lane reductions along King Edward
Avenue.
Alternative Design 2 was
evaluated on the assumption that street light poles would be mounted on the
median, with separate pedestrian level lights located in the road edge along
the sidewalks. The objective of this
arrangement, if constructed, would be to use the light poles to create a
strong, vertical, in-line design statement in the median, creating an
opportunity for a linear gateway treatment as well as calming traffic by
creating a “friction” along the median.
However, Alternative Design 2 can also be constructed with combination
street/sidewalk lighting along the road edge.
This decision would be made during the project’s detailed design
stage. This modification would not
diminish the overall benefits of Alternative Design 2, which would still be
preferred over Alternative Design 1 by a significant margin.
The street light poles,
luminaries and hardware used for King Edward Avenue, may form one of the
principle elements of the gateway treatment along the corridor. Ultimately this distinction may reflect in
the selection of fixtures beyond those identified in the Residential Street
Lighting Policy.
North Section
The
preferred North Section renewal alternative relocates both connections to/from
the Macdonald-Cartier Bridge and both connections to/from Sussex Drive. This alternative shifts traffic away from
adjacent homes, removes unnecessary pavement, significantly improves the area's
pedestrian and bicycle environment and creates sizeable and useable land
parcels adjacent to Boteler Street and the Rideau River.
Four alternative designs were subsequently
identified for this preferred renewal scheme.
The primary differences between them were:
·
whether or
not to retain the existing northbound connection (and structure) to the Bridge;
·
whether or
not to relocate the northbound connection to Sussex Drive away from the Rideau
River;
·
whether to
take the southbound connection from Sussex Drive over or under King Edward
Avenue.
Following detailed evaluation using the
appropriate Natural, Economic, Social and Transportation Criteria, the
preferred alternative design involved relocating both the northbound and
southbound lanes, shifting the northbound Sussex Drive connection away from the
Rideau River, lowering the northbound structure and taking the southbound
connection under Sussex Drive.
North Section Preliminary Preferred Design
The following are the key factors that contribute to the preferred North Section alternative design as shown on Annex ‘E’:
·
it provides good
opportunities to keep the transportation system operational during
construction;
·
it is the
second-most affordable alternative;
·
it provides an
improved transition between the Macdonald-Cartier bridge freeway environment
and the King Edward urban arterial environment;
·
it results in an
efficient use of land and frees up three land parcels of significant size for
use as green space or urban development;
·
it is all within
City of Ottawa property;
·
it is adaptable
for possible future modifications along King Edward Avenue;
·
it provides a
range of opportunities for gateway treatments including architectural and
landscape features;
·
by reducing the
size and number of bridge structures, it has the least effects on the visual
environment and views;
· it improves noise, vibration, and air quality conditions for residents along Boteler Street and at the north end of King Edward Avenue;
·
it provides
the opportunity for continuous, direct and safe pedestrian linkages to Sussex
Drive and to lower town;
· bicycle connections to and from Sussex Drive are provided along the outside curb lanes, with no lane crossing required;
· it provides for a simple and functional connection with Boteler Street and Bolton Street;
· with the recommended eastbound right-turn only connections of both Boteler and Bolton Streets with King Edward Avenue, it is recommended that the one block section of Cumberland Street between these two streets be converted back to two-way traffic in order to maintain local mobility options.
The preliminary preferred design alternatives for each of the four sections of King Edward Avenue have been combined to provide the Recommended Design for King Edward Avenue Renewal as shown on Annex ‘E’. A section-by-section description of key aspects of the Recommended Design follows:
a) South Section: Laurier Avenue north to Rideau Street:
· reconstruction of the existing four-lane road;
· provision of widened 2.0 m sidewalks on both sides;
· provision of wider shared-use curb lanes to accommodate bicycles, off-peak parking and peak period traffic flow;
· burying of overhead utilities;
· changes to the underground utilities including a new watermain and separation of the storm and sanitary sewers;
· provision of new traffic plant at all currently signalized intersections.
b) Central Sections: Rideau Street north to Boteler Street:
· reconstruction of the existing six-lane road, but with elimination of surplus pavement;
· provision of a narrow 1.5 m median to allow the relocation of the road edge further from adjacent buildings, to reduce the pedestrian crossing distances and to provide space for enhanced streetscaping and landscaping;
· provision of widened 2.0 m sidewalks separated from the road edge by a landscaped boulevard;
· provision of 4.5 m shared-use curb lanes to accommodate bicycles, off-peak parking and peak period traffic;
· modifications to the Boteler Street and Bolton Street connections to King Edward Avenue to function as an eastbound only right-turn movement onto King Edward Avenue;
· conversion of the one block section of Cumberland Street between Boteler Street and Bolton Street to two-way traffic flow to improve local traffic circulation;
· provision of “gateway” elements at key intersections;
· burying of overhead utilities;
· provision of a new watermain;
· provision of new traffic plant at all currently signalized intersections;
· the installation of the underground traffic plant at the King Edward/Cathcart intersection to accommodate possible future pedestrian-activated traffic signals at this location if/when warranted, or determined appropriate.
c) North Section: Boteler Street north to Sussex Drive and north to the Macdonald-Cartier Bridge, including the complete reconfiguration of the ramps to/from Sussex Drive and the Macdonald-Cartier Bridge, in order to modify drivers’ perceptions of the corridor, to improve pedestrian and bicycle safety and to improve all aspects of the area’s social environment:
· relocation of the southbound Bridge departure lanes and traffic away from Boteler Street residences;
· relocation of the northbound Bridge approach lanes and traffic adjacent to the realigned southbound lanes to provide more of a Parkway, as opposed to a Freeway environment;
· construction of the new bridge structure at a height of approximately 1.5 m to 2.0 m below the elevation of the existing northbound bridge structure;
· reduction of the northbound connection to Sussex Drive from two lanes to one lane and shift it further away from the Rideau River to maximize the amount of waterfront property;
· relocation of the southbound connection from Sussex Drive to merge with southbound King Edward Avenue on the right side adjacent to the curb, as opposed to its current merge on the left side adjacent to the median;
· provision of 2.0 m widened sidewalks adjacent to both the northbound and southbound connections to Sussex Drive;
· provision of wider shared-use lanes on both connections to/from Sussex Drive to accommodate bicycles and motorized vehicles;
· modifications to the Boteler Street intersection with the new southbound connection from Sussex Drive to function as an eastbound only right-turn movement;
· provision of a major gateway feature at the north end of the Corridor to announce entry to Ottawa and the beginning of a changed roadway environment;
· provision of a new watermain north to Sussex Drive;
·
provision of a new storm sewer outflow
to the Ottawa River to drain the new underpass.
With the resolution of the functional elements of this plan, the next step was to prepare a Streetscape Demonstration Plan that incorporates all the appropriate Planning and Design Principals into the preferred design alternative. This Plan is shown as Annex ‘F’ and will be presented in full scale at the Transportation and Transit Committee presentation.
The following is a summary of the most significant issues raised during the study process and how they were responded to.
Truck Traffic: Many area residents expressed concern about the volume and effects of truck traffic on this corridor and want it removed.
Addressing interprovincial truck traffic is not within this Study's mandate. Until an alternative bridge crossing of the Ottawa River and truck route is provided, King Edward Avenue will have to accommodate trucks.
Traffic Volume: Many area residents expressed concern about traffic volume and the effect of all traffic in this corridor and want both the traffic and the number of lanes reduced.
Vehicle reduction would only be accomplished through significant modal split changes or the provision of a new interprovincial bridge. Investigation of improved interprovincial transit and of new interprovincial bridges are not within this Study's mandate. All existing bridge corridor's primary intersections are currently operating at, or over capacity. Until a new corridor is provided there is no place for displaced traffic to go if King Edward Avenue were reduced to four lanes. The Recommended Design for the Renewal of King Edward Avenue can easily be converted from six lanes to four lanes with minimum cost and without affecting the integrity of the recommended plan.
Maintain Traffic Flow: Many users (commuters, truckers, transit) of the road expressed concern about the importance of maintaining traffic flow and mobility along the corridor.
The recommended alternative design does not reduce the number of lanes or the corridor's capacity.
STO Bus Time Point: Many residents expressed concern about the presence and affect of the lengthy queue of STO buses along the southbound curb lane of King Edward Avenue in the afternoon peak hour.
This was brought to the attention of the STO representative on the Technical Advisory Committee, who following investigation, responded that they did not have an alternative that would not adversely affect bus scheduling and therefore bus ridership. Alternatives to store buses elsewhere along this corridor were examined but no more desirable options were determined. Hence, as this is an operational issue, which does not impact the design of the preferred renewal alternative, it was not investigated further in this study.
Vehicle Speed: Many residents expressed concern about vehicle speed in the Central North and North Sections.
This is a complex issue as a freeway system is currently connecting into an urban roadway with very little distance to affect an appropriate transition. It is hoped that with the recommended North Section design alternative including a gateway entry feature and a Parkway character, drivers will be made more aware of the changing nature of King Edward Avenue and its adjacent land uses and will reduce speeds accordingly. The provision of a parking type "transition zone" will help to modify drive behaviour between the Macdonald-Cartier Bridge freeway environment and the King Edward Avenue urban arterial environment.
Pedestrian and Cyclist Safety: There was expressed concern about pedestrian and bicycle safety along and across the corridor.
Measures incorporated in the Recommended Plan to better accommodate these travel modes include:
Pedestrians:
· 2.0 m sidewalks;
· shorter pedestrian crossing distances across both King Edward Avenue and many side streets;
· a textured, pedestrian-priority crosswalk system;
· pedestrian level lighting;
· a new sidewalk system in the north section linking King Edward Avenue to Sussex Drive, that provides protected crossings of King Edward Avenue;
· the installation of an underground traffic plant at the Cathcart/King Edward intersection in the event that future monitoring determines this to be an appropriate location for pedestrian-activated signals.
Cyclists:
· wide shared-use curb lanes throughout the corridor;
· shorter crossing distances across King Edward Avenue and many side streets;
· relocation of the southbound Sussex Drive to King Edward Avenue roadway connection to merge with King Edward Avenue on the right side adjacent to the curb, and not on the left side adjacent to high speed traffic as currently exists.
Noise, Air Quality and Vibration: This was an expressed concern of many adjacent residents, particularly in the North and Central North Sections.
The recommended North Section alternative design will result in significant noise and air quality improvements, as well as some vibration improvements.
Overall Hostile Corridor: many expressed the unsafe and unattractive nature of the corridor as a whole.
The Recommended Design and Streetscape Plan results in a narrower roadway, improved lighting, burying of overhead utilities, extensive new streetscaping and landscaping and the introduction of strong gateway elements.
Overhead Utilities: as mentioned above, overhead utilities contribute to the current unattractiveness of the corridor and take up valuable space within a very tight corridor.
This study recommended the burying of overhead utilities in accordance with Official Plan Policy 5.10.2 (c). The Recommended Design and Streetscape Demonstration Plan reflect this recommendation.
Gateway Elements: King Edward Avenue is one of the most important gateways into the City of Ottawa. Gateway elements can enhance the visual appeal of a corridor, can announce arrival to and departure from Ottawa and this urban corridor, and can affect driver behaviour by clarifying the transition from the highway realm across the Macdonald-Cartier Bridge to the urban roadway and residential realm south of Boteler Street. The City of Ottawa's Official Plan identifies King Edward Avenue as the first gateway to be improved in the City.
This study recommends the design and implementation of gateway elements in accordance with the former City of Ottawa Official Plan, Section 5.6.2 (r). The Streetscape Demonstration Plan reflects this recommendation.
Surplus Property: with the proposed realignment of King Edward Avenue in the North Section (north of Boteler Street), and of the road connections to/from Sussex Drive, there is surplus City land that is no longer required for roadway purposes. There are many potential uses for these surplus lands, which are located adjacent to the north of Boteler Street and between the realigned road and the Rideau River. There are also adjacent vacant NCC land parcels that raises the issue of consolidation.
This study recommends that the City initiate a study of land use opportunities related to the surplus property in the North Section, that results from the recommended relocation of the King Edward Avenue roadway connections to/from the Macdonald-Cartier Bridge and to/from Sussex Drive.
The project has followed the requirements of a Harmonized Environmental Assessment Process (HEAP). The effects on the surrounding environment (social, physical, biological, transportation) were comprehensively evaluated. In general, the majority of the negative impacts related to the Recommended Alternative Design for the Renewal of King Edward Avenue are associated with the construction activities. These are relatively short-term in nature and can be mitigated through Best Management Practices.
As the Recommended Design Alternative is located all on City of Ottawa property, there are no federal land use approvals required.
There are many longer-term effects of the project which are positive in nature including: renewal of deteriorated and aging infrastructure, improvement to the corridor's pedestrian and bicycle systems, improvement in noise, air quality and vibration particularly in the North Section, potential traffic calming in the North Section and a more visually appealing corridor.
The project has been completed in accordance with the Environmental Assessment process and has included extensive public consultation. Three Public Open Houses were held at the École secondaire publique De la Salle, 501 Old St. Patrick Street, on Wednesday, 07 March 2001, Thursday, 28 June 2001 and Wednesday 29 May 2002.
Methods of meeting notification and information provision included newspaper notices (local and community), distribution of flyers, placement of posters and the use of electronic roadway signs. The Open Houses were very well attended, with sign-ins for each meeting being 121, 148 and 167 persons respectively.
Three focus group meetings were also held during the study with the King Edward Avenue Task Force/Rideau Street BIA, Boteler Street residents and Bolton Street residents to discuss issues of particular concern to each group on the appropriate time throughout the Study.
Numerous meetings were also held with the Technical Advisory Committee (TAC) and the Public Advisory Committee (PAC) at key times during the Study, including prior to each Public Open House.
The TAC was composed of representatives from the City of Ottawa, the Communité urbaine de l'Outaouais, Ministère des Transports au Québec, National Capital Commission, Ontario Ministry of Transportation, Public Works and Government Services Canada, Societé de Transport de l'Outaouais, and Delcan Corporation.
The PAC consisted of 25 members representing the King Edward Avenue Task Force, Community Associations, Business Improvement Areas, Special Interest Groups, the City of Ottawa, the City of Gatineau and Public Works and Government Services Canada.
As a general overview of public comment, there is a desire to have trucks removed from King Edward Avenue and to have a reduction in traffic volume. There was mixed support for a reduction in traffic lanes. In the absence of a new interprovincial bridge in the near term, which when provided could accommodate trucks and regular traffic, there was broad support for the King Edward Avenue Renewal's Recommended Design.
As required under the Municipal Act of Ontario regarding Public
Hearings, a notice of the proposed King Edward Avenue Renewal has been placed
in Le Droit and the Ottawa Citizen for four weeks on 14, 21 and 28 June and 5
July 2002.
CONFORMITY TO THE TRANSPORTATION MASTER PLAN
The guiding principle from the Transportation Master Plan is the
provision of a modal hierarchy with emphasis on walking, cycling and transit
usage. This principle will be reflected
in the detailed design of the sidewalks, pedestrian crossings, traffic signals
and cycling facilities in the King Edward Avenue corridor.
Following the recommendation of the Preliminary Preferred Design, the City retained the services of a local firm to conduct an independent Value Engineering Study (VES) of the work done to date. The findings of the VES were generally consistent with the recommendation of the King Edward Avenue Renewal project. It was in agreement with the recommendations related to the narrow median option and to roadway realignments for the North Section. Relevant recommendations related to the staging of and/or deferral of sections of the Renewal to defer costs and to design details that can be addressed during the next stage of the Study, which is Detailed Design and Contract Document Preparation.
The Cycling Advisory Committee has been contacted at appropriate times throughout the study and representatives have attended PAC meetings. Their comments on the Recommended Design Alternative have been incorporated, as appropriate.
The preliminary construction cost estimate for the recommended King Edward Avenue Renewal Design is approximately $18M (in 2002 dollars). A more accurate total project cost will be developed as detailed design is undertaken.
Funds to initiate design and construction have already been approved in 2001, and are shown in the Internal Order 900061, King Edward Avenue Renewal.
Design is to be initiated in the later half of 2002 with construction likely to occur between 2003 and 2006. A phasing plan will be developed during the detailed design phase, and it will be somewhat dependent on the timing of other major road and bridge rehabilitation projects in the immediate area.
Annex A - Corridor Aerial Photograph
Annex B - North Section Aerial Photograph
Annex
C - Corridor
Sections
Annex D - North Section Preferred Alternative Design
Annex E - Recommended Alternative Design
Annex F - Streetscape Demonstration Plan
A full size Streetscape Demonstration will be presented at the Transportation and Transit Committee meeting.
The Environmental Study Report (ESR) which documents the entire environmental assessment process and study recommendations will be prepared and filed for the 30-day public review period, in accordance with the provincial Environmental Assessment Act.
Subject to approval by Transportation and Transit Committee and Council and the outcome of the filing of the ESR document, the Department will proceed with the detailed design and subsequent construction.