Report to/Rapport au :

 

Transportation Committee

Comité des transports

 

12 August 2011 / le 12 aoùt 2011

 

Submitted by/Soumis par : Nancy Schepers, Deputy City Manager, Directrice municipale adjointe, Infrastructure Services and Community Sustainability, Services d'infrastructure et Viabilité des collectivités

 

Contact/Personne ressource: Vivi Chi, Manager/Gestionnaire, Transportation Planning/Planification des transports, Planning and Growth Management/Urbanisme et Gestion de la croissance

(613) 580-2424 x 21877, Vivi.Chi@ottawa.ca

 

Gloucester-Southgate (10), Osgoode (20), Gloucester-South Nepean (22)

Ref N°: ACS2011-ICS-PGM-0120

 

SUBJECT:

Bank Street Widening (Leitrm Road to Rideau road) ENVIRONMENTAL ASSESSMENT Study – Statement OF WORK

OBJET :

Étude d’évaluation environnementale sur l’Élargissement de la rue Bank (entre les chemins Leitrim et Rideau) – Énoncé des travaux

 

 

REPORT RECOMMENDATION

 

That the Transportation Committee approve the Statement of Work for the proposed Bank Street widening from Leitrim Road to Rideau Road Environmental Assessment Study, as detailed in Document 1.

 

RECOMMANDATION DU RAPPORT

 

Que le Comité des transports approuve l’Énoncé des travaux de l’Étude d’évaluation environnementale proposée pour le projet d’élargissement de la rue Bank entre les chemins Leitrim et Rideau, comme le décrit le document 1.

 

 

BACKGROUND

 

Bank Street is a major north-south arterial road in Ottawa.  Beginning at Wellington Street in the downtown area, Bank Street runs south through the neighbourhoods of Centretown, the Glebe, Old Ottawa South, Alta Vista, Hunt Club, Blossom Park, and Leitrim, which is at the City’s urban boundary.  Bank Street then continues south through the rural villages of South Gloucester, Greely, Metcalfe, Spring Hill, and Vernon, before exiting the City limits.  From Wellington Street to Leitrim Road, Bank Street is a four lane urban arterial roadway narrowing to a two lane rural roadway just south of Leitrim Road, where a growing community resides.

 

In response to increased pressures for development, Council approved the Leitrim Community Design Plan (CDP) in July 2005.  The Leitrim community lies south of Leitrim Road, bordered by Albion Road to the west and Bank Street to the east.  Largely undeveloped at the time, the CDP provides a detailed development concept plan, guides future development, and identifies a recommended road network within the Leitrim community. 

 

Rapid growth in this area has increased traffic volumes on Bank Street leading to congestion during the peak periods.  The City has recently approved the “Findlay Creek Stage 2” development application, consisting of 703 residential units.  A condition of development is to extend Findlay Creek Drive to Albion Road since Bank Street is currently the only access to the Leitrim community.  Completion of Stages 1 and 2 of the Findlay Creek development is anticipated in 2012/13 and will total approximately 1420 dwelling units.  The traffic impact study undertaken for Stage 2 development indicates that traffic volumes to accommodate this growth on Bank Street will exceed capacity by 2014 and widening of Bank Street will be required.

 

 

DISCUSSION

 

The City’s Transportation Master Plan (TMP) identifies the widening of Bank Street to four lanes from Leitrim Road to the urban boundary in Phase 2 (2016-2022) and further south to Mitch Owens Drive in Phase 3 (2023-2031).  Under provincial legislation, an Environmental Assessment (EA) study is required prior to widening of Bank Street.  This report provides the terms of reference for the EA study and outlines the Statement of Work (SoW), described in Document 1. 

 

The study limits, shown in Figure 1, will extend from Leitrim Road to Rideau Road, beyond the TMP’s Phase 2 limit of the Urban Boundary.  This is in response to a Council approved motion for the planned rezoning of a pilot project for the Rideau Carleton Raceway (RCR) to assess the transportation infrastructure needs in this area.  While the transportation infrastructure needs of the RCR will be examined as part of the next TMP update from a network perspective, this EA study will take the development of the RCR into consideration as a source of demand impact on Bank Street.

 

In addition to the RCR rezoning, the Central Canada Exhibition is proposing to relocate the SuperEX in 2012 permanently to a site in the vicinity of Rideau Road and Albion Road and the transportation impact on the road network also needs to be considered.

 


Figure 1:  Bank Street Widening EA Study Limits

 

BANK ST EA LOCATION PLAN-2.wmf

 

Key considerations for this EA study include the following:

 

·         Detailed evaluation of future transportation demand for the City’s north-south direction of travel and public areas of interest;

·         Cycling and pedestrian needs in the arterial roadway corridor;

·         Full evaluation of any potential impacts on wetlands and other natural environment areas;

·         Preserving the rural character of rural areas; and

·         Effects on existing community.

 

 

ENVIRONMENTAL IMPLICATIONS

 

The study will examine and evaluate the project’s effects on social, cultural, physical, and natural environments within the study area.  Appropriate mitigation measures will be developed and post mitigation environmental impacts will also be determined.

 


RURAL IMPLICATIONS

 

The study area lies within the City’s urban area to the west and rural area to the east of Bank Street.  Potential impacts on the rural character, rural residents, and any active farming operations will be incorporated in the study.  Traffic demand originating from existing and future residents of the rural areas will also be incorporated into the study process.

 

 

CONSULTATION

 

Consultation with stakeholders, public agents, and individuals will be an integral component of the EA study.  The consultation process will include meetings with key stakeholders through the Agency Consultation Group, Public Consultation Group, and Business Consultation Group.  Consultation with the general public will occur principally through open houses and also through the project web page, e-mail, and additional meetings as required.

 

 

COMMENTS BY THE WARD COUNCILLOR(S)

 

Councillor Deans provided the following comments:

1.      Please include the Rideau Carleton Raceway and Slots as a member of the Business Consultation group and consider the impact of the Rideau Carleton Raceway and Slots operation on Bank Street.

2.      Please identify the need for future studies to address downstream effects on existing roadways such as Conroy, Kemp, Orville Kemp, Leitrim, Lester, Bank and Walkley Roads.

3.      Please explore the possibility of including HOV lanes and, or dedicated bus lanes as part of the E.A. analysis.

 

Councillor Thompson indicated concurrence with this report.

 

Councillor Desroches indicated he supports planned upgrades to Bank Street given the growth in the Findlay Creek and Leitrim area. His comments are as follows:

This important infrastructure work will support the City’s pedestrian, transit and cycling objectives.  There is growing demand for improved cycling facilities in this area, especially for employees of CFB Leitrim.  The planned sidewalks will also improve pedestrian access and improve connectivity to the City of Ottawa recreational facilities at the Fred Barrett arena.  Bank Street is a gateway to the Nation’s capital and should have appropriate urban infrastructure.  Transit in the area will be enhanced by improving the reliability of the service along Bank Street.  The study should also include upgrades to the Leitrim Road approaches to Bank Street.  This south area road work is important given the growth in the area, access to the Ottawa airport, the new trade and conference centre and the Rideau Carleton Raceway.

 

 

LEGAL IMPLICATIONS:

 

There are no legal implications associated with this report.

 

 

RISK MANAGEMENT IMPLICATIONS:

 

There are no risk management implications associated with this report.

 

 

CITY STRATEGIC PLAN

 

The recommendation contained herein aims to support the following Strategic Directions adopted by Council:

 

Transportation

 

Objective 1: Improve the City’s transportation network to afford ease of mobility, keep pace with growth, reduce congestion and work towards modal split targets.

 

Planning and Growth Management

 

Objective 3: Ensure that the City infrastructure required for new growth is built or improved as needed to serve growth.

 

 

FINANCIAL IMPLICATIONS

 

Funding for this study is available under capital account # 905396 – 2011 Environmental Assessment Studies Arterial Roads.

 

 

SUPPORTING DOCUMENTATION

 

Document 1    Bank Street Widening from Leitrim Road to Rideau Road EA Study – Statement of Work.

 

 

DISPOSITION

 

Following Committee approval of the attached Statement of Work, the selection of consultants will commence.  A call for proposal will be undertaken under the direction of Supply Management Branch.

 

 


BANK STREET WIDENING FROM

LEITRIM ROAD TO RIDEAU ROAD                                                              DOCUMENT 1

 

INTRODUCTION

 

The City of Ottawa is the proponent of a Class Environmental Assessment (EA) Schedule C to study the proposed widening of Bank Street from Leitrim Road to Rideau Road.  This Statement of Work describes the City’s intentions with respect to the methodology, public consultation and deliverables for this study.

 

PLANNING CONTEXT

 

In response to increased pressures for development, Council approved the Leitrim Community Design Plan (CDP) in July 2005.  The Leitrim community lies south of Leitrim Road, bordered by Albion Road to the west and Bank Street to the east.  Largely undeveloped at the time, the CDP provides a detailed development concept plan, guides future development, and identifies a recommended road network within the Leitrim community. 

 

Rapid growth in this area has increased traffic volumes on Bank Street leading to congestion during the peak periods.  The City has recently approved the “Findlay Creek Stage 2” development application, consisting of 703 residential units.  A condition of development is to extend Findlay Creek Drive to Albion Road since Bank Street is currently the only access to the Leitrim community.  Completion of Stages 1 and 2 of the Findlay Creek development is anticipated in 2012/13 and will total approximately 1420 dwelling units.  The traffic impact study undertaken for Stage 2 development indicates that traffic volumes to accommodate this growth on Bank Street will exceed capacity by 2014 and widening of Bank Street will be required.

 

The City’s Transportation Master Plan (TMP) identifies the widening of Bank Street to four lanes from Leitrim Road to the urban boundary in Phase 2 (2016-2022) and further south to Mitch Owens Drive in Phase 3 (2023-2031).  Under provincial legislation, an Environmental Assessment (EA) study is required prior to widening of Bank Street.

 

The study limits, shown in Figure 1, will extend from Leitrim Road to Rideau Road, beyond the TMP’s Phase 2 limit of the Urban Boundary.  This is in response to a Council approved motion for the planned rezoning of a pilot project for the Rideau Carleton Raceway (RCR) to assess the transportation infrastructure needs in this area.  While the transportation infrastructure needs of the RCR will be examined as part of the next TMP update from a network perspective, this EA study will take the development of the RCR into consideration as a source of demand impact on Bank Street.

 

In addition to the RCR rezoning, the Central Canada Exhibition is proposing to relocate the SuperEX in 2012 permanently to a site in the vicinity of Rideau Road and Albion Road and the transportation impact on the road network also needs to be considered.

 


Key considerations for this EA study include the following:

·         Detailed evaluation of future transportation demand for the City’s north-south direction of travel and public areas of interest.

·         Cycling and pedestrian needs in the arterial roadway corridor.

·         Full evaluation of any potential impacts on wetlands and other natural environment areas.

·         Preserving the rural character in the rural areas.

·         Effects on existing community.

 

PROJECT SCOPE, TASKS, AND DELIVERABLES

 

1.         General

 

The study will be consistent with the approach and requirements set out in the Provincial Environmental Assessment Act.  Federal EA requirements may also be required if federal lands, permits, and funding are impacted. All relevant environmental inventories and analysis undertaken for this assignment will be of sufficient scope to satisfy both Federal and Provincial EA requirements.

 

1.1       Study Area

 

The primary study area, shown in Figure 1, includes the Bank Street Road corridor from Leitrim Road to Rideau Road.  The study area may be adjusted as necessary in order to comprehensively identify the influences on, and the effects of the undertaking as options are developed.

 

 


Figure 1 - Proposed Study Area

 

BANK ST EA LOCATION PLAN-2.wmf

 

1.2       Timing

 

The study is expected to be completed within approximately 18 months.

 

1.3       Co-ordination with Concurrent Studies

 

The EA Study process will take into consideration any information including analysis and preliminary findings of concurrent on-going transportation, development and infrastructure projects that could influence the direction and/or conclusions of the Study. These projects include:

 


1.4       Background Material

 

Relevant background material will be collected and reviewed. This includes:

 

1.5       Summary of Deliverables

 

The deliverables for the study include:

 

2.         Study Design

 

A Study Design will be developed to ensure that all aspects of the EA will be addressed.  Part of this task will be to liaise with the Provincial and Federal authorities responsible for EA reviews to obtain their input on what EA requirements must be met (specific to this project).  The Study Design will:

 

o   Transportation planning and design;

o   Urban planning;

o   Natural environment;

o   Storm Water Management/Hydrology;

o   Geotechnical;

o   Social environment;

o   Municipal/Utilities;

o   Noise;

o   Vibration;

o   Structural;

o   Air quality;

o   Archaeology;

o   Heritage; and

o   Landscape architecture.

 

 

2.1       Identify a List of Stakeholders

 

This study will involve a number of stakeholders, including community groups, property owners, businesses, approval agencies and special interest groups.  Early in the study process, stakeholders will be identified.  This will be accomplished through various forms of consultation, including liaison with Ward Councillors.

 

2.2       Consultation Program

 

This study will examine a wide range of technical, social and environmental issues and will incorporate a broad number of community and business interests. The success of this effort is contingent on an effective, comprehensive and timely consultation program.

 

The consultation process will include meetings with key stakeholders as well as an Agency Consultation Group (ACG), a Public Consultation Group (PCG), and a Business Consultation Group (BCG).  The membership, roles and responsibilities of these groups will be refined through the Study Design, and include a general invitation to all City Advisory Committees.

 

Consultation with the general public will occur principally through Public Open Houses, but also through the project Web page and by e-mail.  Additional meetings with specific agencies, groups or individuals will be held as required in order to address any particular issues as they may arise.

 

3.         Environmental Assessment

 

The undertaking of the Environmental Assessment comprises the following tasks outlined below.

 


3.1       Project Need

 

The Class EA work begins with the review of the need and justification for the proposed widening of Bank Street from Leitrim Road to Rideau Road.  Although this proposed widening has been identified in the TMP, the need for additional arterial capacity and an examination of need and assumptions is required under the Provincial Environmental Assessment Act.  This exercise will be carried out by forecasting travel demand for the south end of the City and determining both existing and future needs for a facility with respect to the impact on north-south travel demand/distribution, economic benefits and links to major employment destinations.  In addition, the study will identify current and projected transportation problems and opportunities within the study area.

 

3.2       Existing Conditions

 

An inventory of the social, economic (agricultural, employment, retail etc.), physical and natural environments within the study area will be compiled. The inventory will consider all available background material and where necessary, supplement this information through on-site surveys and/or detailed studies. The inventory must be of sufficient detail to enable the analysis and evaluation of alternative transportation solutions, designs and mitigating measures.

 

In general, the inventory will identify and describe those aspects of the environment that could potentially affect, or be affected by the undertaking.  Some of the specific aspects of the environment associated with this project include:

 

The existing conditions must be completed for the entire study area so that as alternative solutions and designs are developed and analyzed, the cumulative effects can be examined.  It must also be broad enough to fulfill both Provincial and Federal EA requirements.

 

3.3       Alternative Solutions

 

The Study will identify and examine all reasonable alternatives to the widening of Bank Street from Leitrim Road to Rideau Road.

 

The key components of this stage include:

o   Do nothing;

o   Expand and enhance public transit service (including Park and Ride Facilities) to/from the south suburban areas and rural villages;

o   Expand and enhance cycling routes;

o   Implement transportation demand management (TDM) measures to reduce travel demand; and

o   Expand other arterial roadways in the north-south direction;

 

The different alternative solutions and designs will be developed with input from the Consultation Groups and will be presented to the public for comments at several Public Open Houses throughout the study.

 

The travel-forecasting component included in this stage of the EA must:

 

3.4       Design Alternatives

 

The study will identify and evaluate various design alternatives for the selected solution.  Alignment and cross-section design alternatives will be identified based on consideration of constraints within the study area, input from the public and approval agencies, landowners, as well as City guidelines/standards/practices.  All proposed designs will include any required modifications on connecting roadways (public or private).

 

3.5       Evaluation Criteria and Evaluation Process

 

A comprehensive evaluation criteria and methodology will be developed to evaluate the various alternative designs.  The evaluation process will be clearly described and documented.

 

3.6       Impact Assessment

 

The effects of each alternative design on the environment will be thoroughly evaluated.  Mitigation measures and associated implications (e.g. cost of mitigation etc.) are to be identified and considered in the evaluation process.  The study must clearly identify the initial impacts of each alternative as well as the net post-mitigation effect using quantifiable indicators and measures wherever possible.

 


Effects on traffic operations will be evaluated in accordance with current City guidelines and practices. To ensure that all impacts are appropriately evaluated, detailed studies will be required for certain issues such as:

 

3.7       Costing

 

Developing an accurate project baseline budget is an essential component of this study and it will contribute to the City’s short and long range capital budget forecasting, priority setting, and development charges strategy.  The project budget will also form the basis for funding discussions with senior levels of government, where appropriate.  The baseline budget will be developed using a Work Breakdown Structure (WBS) format in current dollars, and include contingency allowances.

 

Project costing is a fundamental criterion in the evaluation of alternatives and will be a key consideration in the analysis of staging considerations and to establish implementation strategies.

 

3.8       Recommended Plan

 

Following the evaluation of alternatives and determining all necessary mitigation measures to minimize any adverse impacts of the project, a recommended plan will be developed.  This will include:

 

The recommended plan will clearly identify and set out the requirements and timing for all subsequent approvals required to proceed with the construction phase of the project.  The recommended plan will be presented to Transportation Committee and Council for approval.

 


3.9       Environmental Study Report

 

An Environmental Study Report (ESR) will be prepared to document the entire study process including the approved design, mitigation measures, and consultation efforts.  The ESR will be placed on public record for a minimum 30-day review period as per the Environmental Assessment Act.

 

4.         Consultation

 

Consultation with public agencies, private groups, City Advisory Committees and individuals is an integral component of this Study.  The consultation process will include meetings with key stakeholders through an Agency Consultation Group (ACG), a Public Consultation Group (PCG), a Business Consultation Group (BCG), and the general public through Public Open Houses.  A minimum of three meetings with each Consultation Group will be held during the course of the study.  Representation on the ACG, PCG, and BCG, will be confirmed during the development of the Study Design and in consultation with Ward Councillors.

 

4.1       Agency Consultation Group

 

An Agency Consultation Group (ACG) will be formed to provide input on planning, engineering and environmental issues and will provide general guidance to the Study Team.  ACG members will include experts in their related fields from government agencies and approval bodies including, but not limited to:

 

4.2       Public Consultation Group

 

A Public Consultation Group (PCG) will be formed to enable private groups to provide direct input to the study, advising and commenting on local issues and concerns.  PCG members may include representatives from local community groups, special interest groups, and adjacent property owners.  Membership of this group will be determined in consultation with affected Ward Councillors.

 

4.3       Business Consultation Group

 

A Business Consultation Group (BCG) will be formed to enable business representatives to provide direct input to the study, advising and commenting on local issues and concerns. 

 

4.4       Notifications

 

The public will be notified at appropriate stages in the Study pursuant to the Environmental Assessment Act.  Each announcement will take the following forms:

 

4.5       Public Open Houses

 

The Public Open Houses (POHs) will be held to present and obtain feedback on existing conditions, alternative design concepts, and the recommended plan.  The EA assignment will include a minimum of three POH meetings that includes a formal presentation and question and answer period as each POH.  The POHs will be advertised in daily and local newspapers and notification will be e-mailed to persons on the Project’s Master Mailing List. 

Background and presentation material will include a Project Update Newsletter which will summarize the information presented at the POH and will be available for general distribution.  All material presented at the POH meetings as well as the Project Update Newsletter will be bilingual.  Bilingual staff will be present during all Public Open House meetings.  A summary report will be produced to document each POH including all comments received.

 

4.6       Project Master Mailing List

 

A Master Mailing List will be prepared and updated via Public Open Houses, general enquiries, e-mails and other forms of consultation.

 

4.7       Project Web Page

 

A Project Information Web Page for the Study will be established on the City’s external web site to inform the public of the progress of the study and upcoming meetings or activities, post the bilingual materials presented at each Open House, and provide a point of contact for e-mail correspondence.

 

4.8       Frequently Asked Questions

 

To assist in providing information to the public, a Frequently Asked Questions (FAQ) will be prepared to provide answers to common questions raised during the study.  The FAQ document will be established early in the study process and will be updated regularly.  It will also be posted on the web site.