Report to/Rapport au:
Transportation and Transit Committee/
Comité des transport et des
services de transport en commun
and Council/et au Conseil
10 June 2002/ le 10 juin
2002
Submitted by/Soumis par: R.T. Leclair, General Manager/Directrice générale
|
|
Ref N°: ACS2002-TUP-TRF-0017 |
SUBJECT: MAIN STREET TRANSPORTATION STUDY -
IMPLEMENTATION OF MEASURES ON GREENFIELD AVENUE
OBJET: ÉTUDE DU TRANSPORT DANS LA RUE MAIN – MISE EN OEUVRE DE MESURES VISANT
L’AVENUE GREENFIELD
REPORT RECOMMENDATIONS:
That the Transportation and Transit Committee recommend Council
approve:
1.
Intersection
narrowings on Greenfield Avenue at Montcalm Street;
2. The construction of a new concrete sidewalk on the east side of Greenfield Avenue between Concord Street and Montcalm Street;
3. Intersection and roadway narrowings on Greenfield Avenue at Concord Street, in the northeast, southeast and southwest quandrants;
4.
The construction of
a centre median and associated lane width reduction at the north leg of
Greenfield Avenue and Concord Street intersection;
5. Removal of the channelized right turn and concrete island at the southeast corner of Greenfield Avenue and the Highway 417 (Queensway) westbound on-ramp; and,
6.
The construction of a new concrete sidewalk on the east
and south sides of Greenfield Avenue between the Highway 417 (Queensway)
westbound on-ramp and King Edward Avenue, and the relocation of the existing
centre median to allow for the new sidewalk.
Que le Comité des
transports et des services de transport en commun recommande au Conseil
municipal d’approuver :
1.
le rétrécissement de l’intersection
de l’avenue Greenfield et de la rue Montcalm;
2.
la
construction d’un nouveau trottoir en béton du côté est de l’avenue Greenfield
entre la rue Concord et la rue Montcalm;
3.
le
rétrécissement de l’intersection et de la chaussée sur l’avenue Greenfield, à
l’angle de la rue Concord, dans les secteurs nord-est, sud-est et sud-ouest;
4.
la
construction d’un terre-plein central et la réduction connexe de la largeur de
la chaussée au tronçon nord de l’intersection de l’avenue Greenfield et de la
rue Concord;
5.
l’enlèvement
du virage à droite à circulation dirigée et de l’îlot en béton à l’angle
sud-est de l’avenue Greenfield et de la bretelle d’accès en direction ouest de
l’autoroute 417 (Queensway); et,
6.
La
construction d’un nouveau trottoir en béton des côtés est et sud de l’avenue
Greenfield, entre la bretelle d’accès en direction ouest de l’autoroute 417
(Queensway) et l’avenue King Edward, et le déplacement du terre-plein central
existant en vue de l’aménagement du nouveau trottoir.
The former Regional Council approved the Main Street Transportation Study in June 2000. Council approved funding for the implementation of measures on Greenfield Avenue from Montcalm Street to King Edward Avenue on 11 July 2001 (see Annex 1 for Key Plan). This approval was subject to consultation with the Ward Councillor, and as required, subject to detailed public consultation, the Municipal Act and Environmental Assessment Act, detailed design, and technical circulation. Applicable sections of the Study are included in Annex 2. Detailed design is complete, and a Public Open House meeting and consultation with the Ward Councillor have occurred over the past year. Public notices, as required under provision of the Municipal Act, were placed in daily papers and one formal request to be heard at Transportation and Transit Committee was received.
Due to the extent of some of the changes required from the original study and additional items identified through the detailed design process, this report presents the recommended measures for construction. The purpose of this report is to obtain approval for implementation of measures related to the Main Street Transportation Study. It is not intended to further examine or debate the study process or conclusions.
DISCUSSION
The Main Street Transportation Study recommended intersection narrowings on Greenfield Avenue at Montcalm Street and on the south leg of Greenfield Avenue at Concord Street, as well as a concrete sidewalk on the east side of Greenfield Avenue between Montcalm Street to Concord Street. Staff are recommending that these measures be implemented. However, staff are proposing that an additional narrowing be constructed at the northeast corner at Concord Street and Greenfield Avenue. This narrowing, which was not mentioned in the original study, is intended to improve visibility at this corner, given the angle at which Concord Street intersects with Greenfield Avenue. The proposed modifications are illustrated in Annexes 3A and 3B.
The original study recommended a twenty-five metre long centre median on the north leg of Greenfield Avenue at Concord Street, combined with a reduction in road width along the west curb line, requiring the removal of two on-street parking spaces. At the Public Open House meeting, staff recommended an alternate, with more substantial road width reduction on the west side of the road, in place of the proposed centre median. However, the residents felt that a median would provide added safety for the pedestrians crossing the road at this location, as well as addressing speed of traffic on Greenfield Avenue, particularly in the southbound direction towards Main Street. The Community Association was in unanimous support of the installation of the median. Staff can support the original recommendation, and have revised the design presented at the Public Open House meeting to allow for the centre median, as originally recommended in the Main Street study. See Annex 3B.
At Greenfield Avenue and the westbound on-ramp to Highway 417 (Queensway), an additional roadway modification is being proposed that was not mentioned in the original study. The Study recommended the construction of a new sidewalk on Greenfield Avenue, as described below in Recommendation 6. As part of the design work for this new sidewalk, staff reviewed the appropriateness of modifying this intersection. It is recommended that the channelized right turn and associated concrete island at the southeast corner be removed, in order to reduce the overall pedestrian crossing distance. The existing traffic control signal will be modified to provide for pedestrian crossings at this intersection. This modification will not adversely affect the level of service at this intersection. See Annex 3C.
On Greenfield Avenue, from the Highway 417 (Queensway) on-ramp to King Edward Avenue, the Main Street Study recommended a new concrete sidewalk on the east/south side of the street. In order to construct this sidewalk and to retain the minimum acceptable road width, it is necessary to relocate the existing centre median. The sidewalk cannot be entirely placed at the back of the existing curb lines because of the existing retaining walls under the Nicholas Street and Transitway structures. This was not addressed in the original study and costs to proceed with the sidewalk in this area are substantially more than the original report estimated. See Annexes 3C and 3D.
ENVIRONMENTAL IMPLICATIONS
No environmental implications directly arise from approval of this report.
RURAL IMPLICATIONS
N/A
A Public Open House meeting was
held on 9 April 2002. The Municipal Act, Section 300, requires that public
notice of any modifications to the roadway be published in daily papers for
four consecutive weeks. The Municipal
Act advertisements appeared in local papers from 26 April to 17 May 2002. One
formal request to be heard at Transportation and Transit Committee was
received. See Annex 4.
It should be noted that there
have been minor alterations to some of the above modifications from the
original Main Street Transportation Study. However, public consensus and
support from the Ward Councillor has been obtained on the above modifications.
Section 2.5.6 of the Transportation Master Plan, approved by the former Region, provides direction:
“Consider traffic calming measures as possible solutions to operational or safety problems stemming from excessive automobile speeds or poor driver behavior. In assessing the appropriateness of traffic calming measures on Regional and other roads several factors must be considered, such as:
· impacts on public safety;
· impacts on the functional role of the Regional road in serving regional mobility needs and providing access to adjacent land uses;
· impacts on public and emergency services;
· impacts on adjacent local roadways and neighborhoods;
· liability where accepted design standards are not met; and,
cost.”
FINANCIAL IMPLICATIONS
Funds totaling $135,000 were provided for in Internal
Order 990685 - Area Traffic Management to cover the costs for Recommendations 1 to 5 to be implemented this
year. However, additional funding will be required to implement Recommendation
6 and will be submitted as part of the 2003 Capital Budget.
The Surface Operations Branch
requires additional annual funding in the amount of $8,500 to maintain the
proposed roadway modifications. The funding is required to accommodate the
additional winter maintenance, Spring cleaning, and life cycle (repair) costs.
These funds will be identified in the 2003 Operating Budget.
Annex 2:
Excerpts From Main Street Transportation Study
ANNEX 3B: Proposed Intersection Modifications on Greenfield
Avenue and Concord Street
ANNEX 3C: Proposed Intersection Modifications on Greenfield Avenue
and 417 Ramp
ANNEX 3D: Proposed Intersection Modifcations on Greenfield Avenue
and King Edward Avenue
ANNEX 4: Public Consultation Process
Recommendations
1 to 6
Staff of the Transportation, Utilities and Public Works Department to implement the narrowings, intersection modifications, sidewalks and relocation of the centre median on Greenfield Avenue, between Montcalm Street and King Edward Avenue.
ANNEX 1
No |
Location |
Recommended Measues |
Cost $ |
Stage |
35
|
Greenfield
Avenue
|
Construct
a sidewalk (2m) on the south side of Greeenfield Avenue (between Montcalm
Street and Concord Street). This would improve pedestrian mobility and safety. |
7,000 |
2 |
36 |
Greenfield Avenue |
Consider
widening the existing sidewalks to (2.0m) on both sides of Greenfield Avenue
(between Concord Street and the overhead bridge structure to the east). The existing sidewalks along
this portion of Greenfield Avenue are 1.5m.
Wider sidewalks would improve pedestrian safety in this relatively
high volume/high speed section of Greenfield Avenue. The need for this measure should be
reviewed following the action taken in Items 37 and 39. |
35,000 |
2 |
38 |
Greenfield Avenue and
Montcalm Street |
Construct
curb extensions (2m) at the southeast, southwest, and northwest corners of
the intersection to protect on-street parking areas and reduce the pedestrian
crossing distance. A speed survey conducted on
Greenfield Avenue between Concord Street and Montcalm Street indicated an
average vehicle speed of 54 km/h. The
85th percentile speed was found to be 61 km/h. At the time of design, consider locating
bollards in the curb extension to improve the protection of pedestrians and
cyclists waiting to cross the street.
Vehicles currently park on the
south side of Greenfield Avenue between Montcalm Street and Concord Street
(parking is not permitted on the north side along this street). |
5,000 x 3 = 15,000 |
2 |
40
|
Greenfield
Avenue and Concord Street
|
Construct
curb extensions at the southeast and southwest corners of the intersection
and construct a narrow centre median (1.5m) on the north leg of Greenfield
Avenue. These measures will help to
reduce the amount of pavement, protect the on-street parking, reduce
pedestrian crossing distances and better define traffic flow through this
intersection. A speed survey conducted on
Concord Street at Greenfield Avenue indicated an average vehicle speed of 57
km/h. The 85th percentile
speed was found to be 65 km/h. At the
time of design, consider locating bollards in the curb extension to improve
the protection of pedestrians and cyclists waiting to cross the street. One or two parking spaces would be lost on
the north side of Greenfield Avenue. |
15,000 |
2 |
Annex 3A
Proposed
Intersection Modifications on Greenfield Avenue AND MONTCALM
STREET
Annex 3B
Proposed
Intersection Modifications on Greenfield Avenue and concord street
Annex 3C
Proposed
Intersection Modifications on Greenfield Avenue and 417 ramp
Annex 3D
Proposed
Intersection Modifications on Greenfield Avenue and king edward avenue
Annex 4
Input to the proposed modifications was obtained largely
through one Public Open House meeting on 9 April 2002 at the Old Town Hall on
Main Street. Approximately 50 people
attended the Open House Meeting. Ward
Councillor Clive Doucet was also present.
Comments received are as noted below, and staff responses have been
provided (in italics):
·
Suggested that a
pedestrian crossing be constructed on the east leg of Greenfield Avenue/Concord
Street intersection: Staff cannot
recommend, as this is not a controlled interection.
·
Suggested addition of
illuminated caution signs located on approach from King Edward
Avenue/Greenfield Avenue intersection to reduce speeds on grade change (two
comments): Staff to review and determine if required.
·
Commented that
visibility at Concord Street/Greenfield Avenue intersection is poor: Staff are recommending an intersection narrowing at
this corner to improve visibility.
·
Suggested that stop
signs and/or lights be added at Concord Street/Greenfield Avenue intersection
(two comments): This issue was included in the staff submission to the
former Regional Council, and the decision was not to implement any
additional traffic control (all-way stop or traffic signal) at this location. As the purpose of this report is to obtain
approval on physical changes to the roadway, further discussion on this issue
is not included in this report. The
roadway modifications are designed such that it does not preclude any future
option with respect to the method of traffic control at this intersection.
·
Suggested that a
centre median be installed on east leg of the Concord Street/Greenfield Avenue
intersection (nine comments): Staff
concur and a median is now being recommended.
·
Approval of lane
widths at the Concord Street/Greenfield Avenue intersection: Staff to implement proposed modifications.
·
Suggested that speed
humps be considered (two comments): Speed
humps are being implemented where such a recommendation is part of an approved
study. Traffic Calming Guidelines are currently being prepared by staff to
develop technical warrants for the use of speed humps to be implemented.
·
Request for more
police enforcement (two comments): The
measures proposed are to address speeding issues such that the need for
additional enforcement is minimized.
· Request to remove on street parking near 130 Greenfield Avenue: Staff to review.
·
Noticed that accidents
at Main Street/Greenfield Avenue may be due to line of sight: Staff to
review.
·
Concerned that slowing
on Greenfield Avenue will cause more cut through traffic on Concord
Street/Harvey Street (two comments): The
recommended measures are intended to address the speed of traffic and will not
cause additional cut through traffic.
·
Noted discontent with
removed parking spaces in front of Legion: Parking
spaces are a visibility issues for cars exiting Concord Street, the removal of
these spaces was recommended in the report.
·
Recommended that
narrowing at Concord Street/Greenfield Avenue (southwest corner) be extended
further still: The proposed narrowing is
designed to current standards and further extension will mean the removal of
additional parking spaces.
·
Request to have snow
fences removed from Greenfield Avenue: The snow fence will be removed given
the proposed sidewalk at this location.
·
Suggested that
Greenfield should be widened at Concord to prevent back up from left turning
vehicles: Left turns
lanes are not warranted at this locations. This is contrary to the
Study recommendation.
One
request to be heard at TTC was received from the Municipal Act Advertisement
that appeared in the daily newspapers from 26 April to 24 May 2002. The concerned resident stated, “I request an
opportunity to express my concerns and issues regarding Greenfield work as proposed.” As no specific issues were raised by the
resident, staff are not able to provide comments at this time.